mcgrath logo

314-772-7600
1920 S. Kingshighway Blvd.
St. Louis, MO 63110

Ameren-Bland Substation

October 1, 2015

Ameren Missouri’s new $1.8 million Bland substation in Owensville, Missouri provided additional capacity for electrical distribution. The 5.5-acre expansion of the 345 kV substation work included 206 deep foundation piers and a new transformer pit. The rocky project site required substantial earthwork to prepare for construction. All of the excavated rock removed during grading was recycled as bank stabilization. Work Performed Civil/Site Contractor Energy & Industrial Division Page

Read More

Ameren-Cape Girardeau Transmission Line

March 12, 2015

This project involved replacement of wood pole power line structures along Cape Girardeau’s river wall with new steel poles.  This project was immediately adjacent to existing active rail lines. McGrath self-performed the deep foundations for the new transmission line.  Due to the proximately of the river, all foundations were installed utilizing a slurry method of construction.  McGrath coordinated all activities with the rail line, including daily mobilization of flaggers to the site.  Upon completion of [...]

Read More

Ameren-Central Substation

October 1, 2015

McGrath performed civil site work including excavation/backfill, foundations, concrete retaining walls, fencing and security on the three-and-a-half acre Ameren St. Louis Central Substation project in downtown St. Louis. The project included installation of 338 concrete pier foundations for the substation, some of them 8’ in diameter and 60’ deep. General contractor services totaled $3.7 million. McGrath managed a strict, sequenced schedule and coordinated the work of multiple trades. The tight and congested work site required careful [...]

Read More

Ameren-Dorsett Training Building

December 9, 2014

McGrath served as the Construction Manager and General Contractor for the construction of the $900,000, 3,990-square-foot expansion to the existing Training Building at Ameren’s Dorsett Road campus.  This facility provides classroom and workshop space for Ameren’s electrician's to receive additional training. The project consisted of a McGrath furnished Butler Brand Pre-Engineered Metal Building for the shell.  It included new personnel shower and restrooms, a first floor and second floor classroom, two emergency egress exterior stair [...]

Read More

Ameren-Fenton Substation

The first phase consisted of a settlement control system installation due to the flood plain, approximately 12’ high stamped retaining walls on two sides due to the narrow site, and then backfilling of the substation yard area to allow for the piers to be drilled without interfering with the sand drain system.  The sand drain system required a 30 day settlement period prior to any further work taking place. The second phase consisted of site [...]

Read More